Items of Interest

 

 

 

Optional Sector Plan

The optional sector plan process was established as an alternative to the Development of Regional Impact (DRI) process, pursuant to F.S. § 163.3245. Sector plans approved through comprehensive plan amendments will be initiated by the local government in agreement with the Department of Community Affairs (DCA).

The Detailed Specific Area Plan (DSAP) Boundary was approved by the BCC at the April 8, 2010 meeting. The conceptual long term buildout overlay was incorporated into the EAR Based Amendments. The Adoption Package was approved by the BCC at the June 3, 2010 BCC meeting to be transmitted to the DCA. The Notice of Intent & Statement of Intent was received July 21, 2010.

Sector Plan Portion of EAR Adoption Package

Map-Optional Sector Plan

For more information on the optional sector plan process please click the Florida Department of Community Affairs (DCA) link on the right.

OPTIONAL SECTOR PLAN SCHEDULE
Escambia County has contracted with Miller, Sellen, Connor & Walsh, Inc. (MSCW) in the preparation of an Optional Sector Plan pursuant to F.S. § 163.3245.

Status Report

  • Completed Alternative Land Use Plan
  • Developed the Trend Analysis - representing a pattern of development based on our current trends.
  • Developed the Sector Profile.
  • Executed the formal agreement for authorization with the Department of Community Affairs on April 3rd, 2008.

Archive of Recent Meetings:

Milestone Key Dates

05/06/07 DCA reserves a place for Escambia County to complete the Sector Plan
08/08/07 Project Manager issued “Notice to Proceed” to MSCW
09/13/07 RPC held official Scoping Meeting
10/04/07 Approved Memorandum of Understanding with the development group
10/15/07 Regional Planning Council approves of the Optional Sector and forwards a favorable
recommendation to the DCA
10/30-31/08 Stakeholder Interviews
1/22/08 Public Explanatory Workshop held at Ransom Middle School
3/10/08 Public hearing to approve the formal agreement between Escambia County and the DCA
04/08 Completed Trend Analysis
04/16/08 Public Explanatory Workshop held at Ransom Middle School
06/08 Working on Sector Plan Alternatives
10/08 Expected dates for next Public Workshops
03/09 Sector Plan Alternatives completed
08/09 Final conceptual overlay district complete
09/09 Review of goals, objectives and policies
10/09 Transmittal hearing has been delayed until after the adoption of the EAR Based Amendments.

Note: The information on this page is based on best available data, and is provided for information purposes only. Updates will be done as more current data becomes available.